 PMP考试试题一:

Company ABC adopt year-summary for decritiation of asset. They spent $17,000 purchasing one computer. It is estimated that the computer can be sold with $2, 000 three years later. Thus, how much will be the asset decritiation of this computer in year three?

A. 5000

B. 4500

C. 7500

D. 2500

ABC公司通常用年和法来计算资产的折旧。他们花1.7万元买了一台计算机,估计三年后能卖2000元。那么第三年的折旧是多少?

A. 5000元

B. 4500元

C. 7500元

D. 2500元

PMP参考答案:D. 2500元

PMP答案解析:折旧--年数总和法

PMP考试试题二:

Your manager gives you a project charter and asks you to begin working immediately and to provide her with a schedule. what should you do FIRST?

A.Begin estimating the activities necessary to complete the scope of work.

B.Begin creating a project scope statement

C.Create an activity list and then begin to assign the activities to resources.

D.Identify a team and obtain approval for their participation from their functional managers.

项目经理给了你项目章程后要求你立即开始工作,并要求提供给他进度计划。此时,你首先应该做什么?

A.估算活动以确定工作范围。

B.开始制定项目范围说明书。

C.开始制定活动清单,然后给活动分配资源。

D.确定团队成员,并从职能经理那里获得批准。

审题:此题关键字是“给了你项目章程后要求你立即开始工作,并要求提供给他进度计划”“首先应该做什么”,很显然在问在项目章程和进度计划之间的项目步骤,可以从单个项目的项目管理过程章节之规划过程组中查找,也可以从Rita流程图中查找。

定位:规划过程组·单个项目的项目管理

解析:在制定进度计划之前,必须先完成范围说明书和其他活动规划。 规划过程的第一步就是指定项目范围说明书。故选项A、C和D开始之前必须先完成选项B所指的项目范围说明书的制定。

PMP参考答案:B.开始制定项目范围说明书。